Kotilinga Kshetram Progress
2024

February

  • Land clearing in progress
  • Architect design & development drawings are in progress

January

  • Geotechnical exploration in progress
2023

Dec

  • 111 feet Annamacharya Bronze Vigraham making in progress.

Oct

  • Civil and Structural engineering design work in progress

Aug

  • Kailasa Dwaram entrance to the project approved by TN Dept. of Transportation (TDOT)

June

  • Performed Annamayya Vigraha Nirmana Mahotsavam

Mar

  • Appointed sculptor in India to make all Bronze Vigrahams
2022

August

  • Shanku Stapana on August 5 to 7, 2022

June

  • Received approval of the project from Shelby County officials.

April

  • Received the first shipment of Lingams from India.

2021

October

  • Successfully completed Bhoomi Pooja on Oct 16, 2021

April

  • Acquired a Steer and a Calf.
  • On Ugadi day we inaugurated the Sri Venkateswara Gokulam.

March

  • Built the Cow Barn and Shed.

February

  • Topographic survey happened by Civil Engineering Firm.

January

  • Sri Venkateswara Gokulam project was announced to the public for funds.

2020 – Bhoomi Pooja

August

  • Hired Civil Engineering Firm for grading.

July

  • Structural Engineering Firm completed Architectural Design Development documents.

June

  • Structural Engineering contract signed.

April

  • The Engineering firm submitted the initial conceptual design drawings.

March

  • Sri Narayani Amma of Sri Puram blessed the project and suggested to acquire a cow to Graze on the Kotilinga Kshetram area for sanctification.
  • Acquired and paid for 157 major Banalingas from Omkareswar and made arrangements for supply of 1 Crore 2-inch Banalingas from the same vendor.

February

  • Structural Engineer was identified, interviewed.

January

  • The Project was announced to the public. Public support was very enthusiastic and close to $ 2 million were Pledged.